This example demonstrates how to programmatically change the Scheduler's view. To do this you should change the value of the ActiveViewType property. For instance, changing this property's value to DevExpress.XtraScheduler.SchedulerViewType.Week will force the scheduler to use its WeekView options.
C# |
using DevExpress.XtraScheduler;
schedulerControl1.ActiveViewType = SchedulerViewType.Day;
schedulerControl1.ActiveViewType = SchedulerViewType.WorkWeek;
schedulerControl1.ActiveViewType = SchedulerViewType.Week;
schedulerControl1.ActiveViewType = SchedulerViewType.Month;
|
VB |
Imports DevExpress.XtraScheduler
SchedulerControl1.ActiveViewType = SchedulerViewType.Day
SchedulerControl1.ActiveViewType = SchedulerViewType.WorkWeek
SchedulerControl1.ActiveViewType = SchedulerViewType.Week
SchedulerControl1.ActiveViewType = SchedulerViewType.Month
|